TFB / NFC / S is a relative estimation technique that classifies backlog items into three broad categories, rather than assigning them a numerical size: too big, no clue, and small. Its purpose is not to measure, but to quickly identify which items need to be broken down and which require more information before they can be planned.

The technique gained popularity following the release of a deck of estimation cards by Lunar Logic, which replaces the numerical values ​​used in "planning poker" with a minimal set of indicators. The acronym itself is derived from a colloquial and vulgar English expression; for this reason, a more appropriate, "polite" version—"Large / Uncertain / Small"—is typically used in formal settings.

The three categories

Category Meaning What to do with the item
TFB The item is too big to be addressed as is. Break it down before planning.
NFC The team does not have enough information to evaluate it. Investigate, clarify with the product owner, or open an investigation task.
S The item is small enough to fit into a sprint. It can be planned directly.

The asymmetry is deliberate: only one of the three categories allows for progress. The other two are signs that the item is not yet ready.

How to apply it

  1. Gather the items to be classified, typically during backlog refinement.
  2. The team agrees on what "small" means in their context—usually, something that fits comfortably within a single sprint.
  3. Each item is quickly assigned to a category, without lengthy debate.
  4. Items marked as TFB are broken down using story splitting techniques.
  5. Items marked as NFC are addressed to reduce uncertainty—for example, through discussions with the product owner, technical research, or the creation of a prototype.
  6. Items marked as S become available for sprint planning.

The value of the technique lies in its speed: sorting thirty items into three buckets takes minutes, whereas estimating them using points can take up an entire session.

Variants

The original Lunar Logic deck replaces the 'S' category with a card valued at '1': all small items are treated as equivalent, and progress is measured by counting completed items rather than by summing up points. This approach is similar to #NoEstimates, where uniform sizing replaces estimation.

The formal variant Large / Uncertain / Small maintains the same three-category logic, with labels suitable for any professional context.

When to use it

  • During continuous backlog refinement, as an initial filter before performing more detailed estimation.
  • When receiving a large batch of new items that need to be triaged quickly.
  • For teams that want to reduce the time spent on estimation without losing the ability to identify problematic items.
  • As a preliminary step before using more granular techniques, such as the Bucket System or Planning Poker.

Common mistake

Treat NFC as a size, not as an alarm. An item marked as NFC is neither "medium" nor "difficult"—it is an item that the team does not yet understand. If it is left in the backlog with that label and included in the plan anyway, the uncertainty that the technique brought to light enters the sprint unresolved. NFC necessitates action—investigating, asking questions, or prototyping—before the item can move any further forward.

Resources

🔧 Lunar LogicOriginal deck

See also

Want to advance your Agile journey? You can look for upcoming courses and exams, or progress at your own pace by becoming a member of the Agile Club. This membership includes exclusive resources, e-learning classrooms, and access to Skill Arena: a space to practice and measure your Agile skills at your own speed.