Burndown chart

De Scrum Manager BoK
Esta página es una versión traducida de la página Gráfico de avance. La traducción está completa al 100 %.
⏱ 4 min  ·  📅 2026
The burndown chart is a visual tracking tool that shows the remaining work in a sprint over time. It is updated daily and provides early warning of whether the team will finish the committed work before the sprint ends.

It is one of the most common tracking artifacts in Scrum, although it is not part of the standard framework. Its value lies in making the team's pace of progress visible at a glance, without the need for meetings or reports.

Burndown chart

Chart axes and how to read the chart

  • Y-axis (vertical): remaining work, measured in story points, hours, or any unit the team uses.
  • X-axis (horizontal): days of the sprint.

The ideal progress line is the diagonal running from the total committed work at the start of the sprint down to zero on the last day. The actual progress line is rarely perfectly diagonal, but it should stay close to it for the sprint to remain on track.

The shaded area shows the remaining effort

Common patterns

Sprint with normal progress

The actual line fluctuates around the ideal diagonal without drifting away from it to a worrying degree. This is the most common pattern.

Underestimated sprint

The actual line falls more slowly than the ideal one: the work is turning out to be more complex than estimated, and the team will not finish everything it committed to.

Overestimated sprint

The actual line falls faster than the ideal one: the stories were smaller than estimated. The team will finish early and could take on additional work from the Product Backlog.

Updating by stories instead of tasks

When the team works with user stories instead of individual tasks, the chart can be updated for each completed story: all of a story's points are subtracted at once, when it is done. This simplifies chart maintenance and reduces the risk of partial updates (stories that are almost done but never actually get closed).

Common mistake

Updating the chart once a week or at the Sprint Review. The value of the burndown chart lies precisely in early detection: if it is only updated at the end of the sprint, when the problem is already visible, it has lost its purpose. It should be updated daily, even if that happens at the end of the day or at the start of the next one.

Resources

📄 Scrum Master v.4.0 [in Spanish] — Section: sprint trackingFree download · Scrum Manager

📄 Scrum Master en equipos con IA v.1.0 [Scrum Master in Teams with AI v.1.0, in Spanish]Free download · Scrum Manager

See also

Want to advance in agility? You can search for course and exam calls or go at your own pace by becoming a member of the Agile Club. This membership includes exclusive resources, e-learning classrooms, and access to Skill Arena: a space to practice and measure your agile skills at your own pace.