Translations:Gráfico de avance/7/en

De Scrum Manager BoK

Common patterns

Sprint with normal progress

The actual line fluctuates around the ideal diagonal without drifting away from it to a worrying degree. This is the most common pattern.

Underestimated sprint

The actual line falls more slowly than the ideal one: the work is turning out to be more complex than estimated, and the team will not finish everything it committed to.

Overestimated sprint

The actual line falls faster than the ideal one: the stories were smaller than estimated. The team will finish early and could take on additional work from the Product Backlog.

Updating by stories instead of tasks

When the team works with user stories instead of individual tasks, the chart can be updated for each completed story: all of a story's points are subtracted at once, when it is done. This simplifies chart maintenance and reduces the risk of partial updates (stories that are almost done but never actually get closed).

Common mistake

Updating the chart once a week or at the Sprint Review. The value of the burndown chart lies precisely in early detection: if it is only updated at the end of the sprint, when the problem is already visible, it has lost its purpose. It should be updated daily, even if that happens at the end of the day or at the start of the next one.