Characteristics

  • It is an activity parallel to the sprint: it does not interrupt the development in progress, but is carried out alongside it.
  • It is led by the Product Owner, although the team actively participates in estimation and in the analysis of dependencies.
  • The effort it consumes varies with the product and the team, and should be measured in each case; as a guideline, it usually ranges between 5% and 10% of the sprint's capacity.
  • It has a specific goal per session: the aim is not to review the entire Product Backlog, but to make sure that the candidate stories for the next sprint have the necessary level of detail.