The concept is equivalent to what PSP (Personal Software Process) calls "Delta Time": the portion of working time that is genuinely effective work time.

Ideal time vs. elapsed time

The difference between the two has direct implications for planning:

  • Elapsed time: the actual working day. For a team of four people working eight-hour days, the elapsed time in one week is 4 × 8 × 5 = 160 hours.
  • Ideal time: working time under optimal conditions of concentration, without the usual friction.

A basketball game lasts 40 minutes of exact playing time, but the actual game usually runs over an hour. Likewise, a task that "takes three ideal hours" may take up half a working day of elapsed time, because the three hours of effective work are interspersed with meetings, interruptions, and context switches.