How to apply it

  1. Identify the features or user stories to be prioritized.
  2. Estimate the cost of delay of each one, combining the three factors (a relative scale such as Fibonacci can be used).
  3. Estimate the job size of each one.
  4. Calculate the WSJF by dividing CoD by job size.
  5. Sort from highest to lowest WSJF: the first ones are those that generate the most value per unit of effort.
  6. Review iteratively as business needs change.